It is proposed to replace the existing Byfleet 132/33Kv GT2A, 60MVA Grid Transformer with a new transformer rated at 90MVA. This will then match the rating of the GT1A and will permit the firm capacity increase to rise by 37MVA.

Works also included removal of the noise attenuation barrier, disconnection, removal and scrapping of the existing transformer GT2A. All civil works associated with modifying the existing transformer Bay plinth and Bunding arrangements; the Busbar connections and modifications and fencing modifications for GT2A Transformer Bay.

Long O Donnell Associates was awarded the EDF Energy CDM Coordination services framework contract for a period of up to 5 years commencing in October 2008.

The contract required Project Services to include CDM Coordination on EDF HV networks including infrastructure, rail and airport projects.

Client

EDF Energy

Project Value

£1M

Project Duration

2008 - 2013

Services Provided

Archilles Logos RICS Logo