This is Bord Gais Eireann's second interconnection, reinforcing links between Scotland and England.

Beattock to Cluden was the construction of a 30km of 36” high-pressure gas pipeline from Beattock Compressor Station to an AGI at Cluden, comprising of 19 road and rail crossings and 3 major river crossings with high sensitivity.

Long O Donnell Associates provided project management and technical support for the delivery of a cross country pipeline and two above ground installations including such services as permanent materials procurement, programme management, quality assurance/quality control, environmental management, health and safety, commercial and contract management and subcontractor procurement and delivery.

Client

Bord Gáis Éireann

Project Value

£10.5M

Project Duration

12 months

Services Provided

Archilles Logos RICS Logo
Beattock to Cluden 36" Gas Pipeline,

This is Bord Gais Eireann's second interconnection, reinforcing links between Scotland and England.

Beattock to Cluden was the construction of a 30km of 36” high-pressure gas pipeline from Beattock…