Project scope was the replacement and upgrade of the LVAC switchboard and Auxiliary Transformer at Bouverie Place substation.

Works involved the decommissioning, dismantling and removal of existing equipment, and some rearrangement of LVAC circuits working within an operational substation.

Long O Donnell Associates was awarded the EDF Energy CDM Coordination services framework contract for a period of up to 5 years commencing in October 2008.

This contract required Project Services to include CDM Coordination on EDF HV networks including infrastructure, rail and airport projects.

Client

EDF Energy

Project Value

£1M

Project Duration

2008-2013

Services Provided

Archilles Logos RICS Logo
Paddington Integrated Project - Upgrade of Bouverie Place Substation,

Project scope was the replacement and upgrade of the LVAC switchboard and Auxiliary Transformer at Bouverie Place substation.

Works involved the decommissioning, dismantling and removal of existing…